Common use of Concurrent Delay Clause in Contracts

Concurrent Delay. In the event of a Concurrent Delay, Design-Builder shall not be entitled to Delay Costs for the duration of the delay that is concurrent with a delay to the Critical Path for which Design-Builder is responsible. A Concurrent Delay shall not affect Design-Builder’s right to a Completion Deadline adjustment hereunder.

Appears in 2 contracts

Sources: Design Build Agreement, Design Build Agreement

Concurrent Delay. In the event of a Concurrent Delay, Design-Builder Contractor shall not be entitled to Delay Costs for the duration of the delay that is concurrent with a delay to the Critical Path for which Design-Builder Contractor is responsible. A Concurrent Delay shall not affect Design-BuilderContractor’s right to a Completion Deadline adjustment hereunder.

Appears in 1 contract

Sources: Construction Manager / General Contractor Agreement