Concurrent Delay. Notwithstanding the provisions of this ARTICLE VII, Contractor shall only be entitled to a Change Order adjusting the Project Schedule, and not the Contract Price, with respect to any Owner Caused Delay or Force Majeure Event to the extent the Work experienced any mutually occurring or concurrent delays, disruptions, interferences and/or accelerations resulting from causes, events, conditions and/or circumstances caused by a breach by Contractor of its obligations under this Agreement.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (VivoPower International PLC)