Common use of Conflicting Provisions/Order of Precedence Clause in Contracts

Conflicting Provisions/Order of Precedence. The Contract Documents are intended to be complementary and a requirement shown in one Contract Document is intended to be as binding as if included in all Contract Documents. In the event of any conflict or inconsistency between or among the Contract Documents, such conflict shall be resolved in accordance with the following order of precedence: (1) All written modifications and amendments to this Agreement; (2) This Agreement, exclusive of the Appendices; (3) Approved exceptions to RFP Documents as contained and identified in Design-Builder’s Proposal (as negotiated with Owner);