Connection to the System. 4.1.1 The Seller warrants that it has entered into a Connection Agreement with the Buyer, in the Agreed Form, on or before the Signature Date. 4.1.2 The Seller shall give the Buyer at least sixty (60) days' advance written notice of the date on which it anticipates it shall require, in terms of the Connection Agreement the Facility Unit to be connected to the System. 4.1.3 The Parties record that it is intended, in the Connection Agreement, that: 4.1.3.1 the Distributor shall Construct or procure the Construction of the Connection Works on the grids side of metering point. The Distributor will own and operate the network; and 4.1.3.2 the Seller shall Construct the Facility Unit Connection Works to connect the Facility Unit with or to the System and will be responsible for constructing connection works to the metering point.