Connectivity to the grid. i. The Solar Power Developer (SPD) shall be responsible for power evacuation from the Power Project to the nearest designated Delivery Point. The SPD shall construct, operate and maintain the Project during the term of PPA at his cost and risk including the required Interconnection Facilities and in close co- ordination with CTU/STU/DISCOM’s feasibility. ii. The SPD shall seek approval of STU in respect of interconnection facilities iii. The SPD shall undertake at its own cost construction/ upgradation of (a) the Interconnection Facilities, (b) the Transmission Lines and as per the specifications and requirements of STU. iv. The SPD shall undertake at its own cost maintenance of the Interconnection Facilities, excluding the transmission line beyond the Sending Station as per the specifications and requirements of STU, as notified to the SPD, in accordance with Prudent Utility Practices. v. The SPD shall operate and maintain the Project in accordance with Prudent Utility Practices vi. For evacuation facility and maintenance of the transmission, the SPD shall enter into separate agreement with STU/DISCOM, if applicable
Appears in 2 contracts
Connectivity to the grid. i. The Solar Power Developer (SPD) shall be responsible for power evacuation from the Power Project to the nearest designated Delivery Point. The SPD shall construct, operate and maintain the Project during the term of PPA at his cost and risk including the required Interconnection Facilities and in close co- ordination with CTU/STU/DISCOM’s feasibility.
ii. The SPD shall seek approval of STU CTU/STU/DISCOM in respect of interconnection facilities
iii. The SPD shall undertake at its own cost construction/ upgradation of (a) the Interconnection Facilities, (b) the Transmission Lines and as per the specifications and requirements of CTU/STU/DISCOM.
iv. The SPD shall undertake at its own cost maintenance of the Interconnection Facilities, excluding the transmission line beyond the Sending Station as per the specifications and requirements of STUCTU /STU/ DISCOM, as notified to the SPD, in accordance with Prudent Utility Practices.
v. The SPD shall operate and maintain the Project in accordance with Prudent Utility Practices
vi. For evacuation facility and maintenance of the transmission, the SPD shall enter into separate agreement with CTU/STU/DISCOM, if applicable
Appears in 2 contracts
Connectivity to the grid. i. The Solar Power Developer (SPD) shall be responsible for power evacuation from the Power Project to the nearest designated Delivery Point. The SPD shall construct, operate and maintain the Project during the term of PPA EPC at his cost and risk including the required Interconnection Facilities and in close co- ordination with CTU/STU/DISCOM’s feasibility.
ii. The SPD shall seek approval of STU in respect of interconnection facilities
iii. The SPD shall undertake at its own cost construction/ upgradation of (a) the Interconnection Facilities, (b) the Transmission Lines and as per the specifications and requirements of STU/DISCOM.
iv. The SPD shall undertake at its own cost maintenance of the Interconnection Facilities, excluding the transmission line beyond the Sending Station as per the specifications and requirements of STU, as notified to the SPD, in accordance with Prudent Utility Practices.
v. The SPD shall operate and maintain the Project in accordance with Prudent Utility Practices
vi. For evacuation facility and maintenance of the transmission, the SPD shall enter into separate agreement with STU/DISCOM, if applicable
Appears in 1 contract