Construction Completion Phase. 1. Architect shall conduct pre-final inspection and prepare check lists of corrective items, make final inspections (all disciplines), including at least one reinspection, determine the date or dates of Substantial Completion and the date of Final Completion of the Project and Contractor's compliance with the Contract Documents, and recommend acceptance of the Project to Owner. 2. Obtain, review, approve and deliver to Owner written guarantees, manuals and instructions from Contractor as required by the Construction Documents upon completion of construction and prior to Final Acceptance. 3. Architect and its sub-consultants shall correct the original Construction Documents to conform to the Contractor’s project record documents incorporating all as-built changes in the Work, and provide same to Owner within two (2) months of Final Completion of the Project. Record drawings and specifications shall be submitted to Owner on a CD/DVD in CAD and PDF format in accordance with the requirements of Attachment G for Owner’s CAD compliance review. 4. Upon request during the warranty period set forth in the Construction Contract, Architect shall assist Owner in identifying defects in the Project, determine corrective measures, and assist Owner in implementing corrective measures as required under the terms of the Construction Contract.
Appears in 4 contracts
Sources: Architectural Services Agreement, Architectural Services Agreement, Master Agreement for Architectural Services
Construction Completion Phase. 1. Architect Engineer shall conduct pre-final inspection and prepare check lists of corrective items, make final inspections (all disciplines), including at least one reinspection, determine the date or dates of Substantial Completion and the date of Final Completion of the Project and Contractor's compliance with the Contract Documents, and recommend acceptance of the Project to Owner.
2. Obtain, review, approve and deliver to Owner written guarantees, manuals and instructions from Contractor as required by the Construction Documents upon completion of construction and prior to Final Acceptance.
3. Architect Engineer and its sub-consultants shall correct the original Construction Documents to conform to the Contractor’s project record documents incorporating all as-built changes in the Work, and provide same to Owner within two (2) months of Final Completion of the Project. Record drawings and specifications shall be submitted to Owner on a CD/DVD in CAD and PDF format in accordance with the requirements of Attachment G for Owner’s CAD compliance review.
4. Upon request during the warranty period set forth in the Construction Contract, Architect Engineer shall assist Owner in identifying defects in the Project, determine corrective measures, and assist Owner in implementing corrective measures as required under the terms of the Construction Contract.
Appears in 3 contracts
Sources: Engineering Services Agreement, Engineering Services Agreement, Master Agreement for Mechanical and Electrical Engineering Services
Construction Completion Phase. 1. Architect shall conduct pre-final inspection and prepare check lists of corrective items, make final inspections (all disciplines), including at least one reinspection, determine the date or dates of Substantial Completion and the date of Final Completion of the Project and Contractor's compliance with the Contract Documents, and recommend acceptance of the Project to Owner.
2. Obtain, review, approve and deliver to Owner written guarantees, manuals and instructions from Contractor as required by the Construction Documents upon completion of construction and prior to Final Acceptance.
3. Architect and its sub-consultants shall correct the original Construction Documents to conform to the Contractor’s project record documents incorporating all as-built changes in the Work, and provide same to Owner within two (2) months of Final Completion of the Project. Record drawings and specifications shall be submitted to Owner in hard copy and on a CD/DVD in CAD and PDF format in accordance with the requirements of Attachment G for after Owner’s CAD compliance review. Hard copy drawings shall be provided on bond paper.
4. Upon request during the warranty period set forth in the Construction Contract, Architect shall assist Owner in identifying defects in the Project, determine corrective measures, and assist Owner in implementing corrective measures as required under the terms of the Construction Contract.
Appears in 1 contract