Construction of the Complex. (a) The Seller shall commence and proceed with the construction works of the Complex as soon as reasonably practicable following the Effective Date. The Seller shall procure that the design of the construction works shall be carried out with all proper skill and care and in all material respects in accordance with this Agreement, including the Technical Specifications, the Laws of Pakistan (including the Seller Consents and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term. (b) The Seller shall carry out and complete the construction works such that the Seller is able to achieve the Commercial Operations Date by the Required Commercial Operations Date. (c) The Seller shall cause all equipment which is permanently installed by the EPC Contractor as part of the Complex to be new and unused at the time of such installation and to comply with the requirements of Schedules 3.
Appears in 1 contract
Sources: Energy Purchase Agreement
Construction of the Complex. (a) The Seller shall commence and proceed with the construction works of the Complex Construction Works as soon as reasonably practicable following the Effective Date. The Seller shall procure that the design of the construction works Construction Works shall be carried out with all proper skill and care and in all material respects in accordance with this Agreement, including the Technical Specifications, the Laws of Pakistan (including the Seller Consents Consents, the Tariff Determination, the Grid Code and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term.
(b) The Seller shall carry out and complete the construction works Construction Works such that the Seller is able to achieve the Commercial Operations Date by the Required Commercial Operations Date.
(c) The Seller shall cause all equipment which is permanently installed by the EPC Contractor as part of the Complex to be new and unused at the time of such installation and to comply with the requirements of Schedules 3Schedule 2.
Appears in 1 contract
Sources: Energy Purchase Agreement
Construction of the Complex. (a) The Seller shall commence and proceed with the construction works of the Complex as soon as reasonably practicable following the Effective Date. The Seller shall procure that the design of the construction works shall be carried out with all proper skill and care and in all material respects in accordance with this Agreement, including the Technical Specifications, the Laws of Pakistan (including the Seller Consents and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term.
(b) The Seller shall carry out and complete the construction works such that the Seller is able to achieve the Commercial Operations Date by the Required Commercial Operations Date.
(c) The Seller shall cause all equipment which is permanently installed by the EPC Contractor as part of the Complex to be new and unused at the time of such installation and to comply with the requirements of Schedules Schedule 3.
Appears in 1 contract
Sources: Energy Purchase Agreement
Construction of the Complex. β
(a) The Seller shall commence and and/or proceed with the construction works of the Complex as soon as reasonably practicable following the Effective Date. The Seller shall procure that the design of the construction works shall be carried out with all proper skill and care and in all material respects in accordance with this Agreement, including the Technical SpecificationsLimits, the Laws of Pakistan (including the Seller Consents and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term.
(b) The Seller shall carry out and complete the construction works such that the Seller is able to achieve the Commercial Operations Date by in any case no later than the Required Commercial Operations Date.
(c) The Seller shall cause all equipment which is permanently installed by the EPC Construction Contractor as part of the Complex to be new and unused at the time of such installation and to comply with the requirements of Schedules 3installation.
Appears in 1 contract
Sources: Energy Purchase Agreement