Construction of the Complex. (a) The Seller shall commence and proceed with the construction works of the Complex as soon as reasonably practicable following the Effective Date. The Seller shall ensure that the design of the construction works shall be carried out with all proper skill, diligence and care and in all material respects in accordance with this Agreement, including the Specifications, the Laws of Pakistan (including the Seller Consents and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term. (b) The Seller shall carry out and complete the construction works such that the Seller is able to achieve the Commercial Operations Date in any case no later than the Required Commercial Operations Date. (c) The Seller shall ensure and shall procure that the Engineer certifies to the Purchaser before the Commissioning Tests that all equipment permanently installed as part of the Complex is new and unused at the time of such installation, and complies with the requirements of Schedules 2 and 5. (d) The Complex and the components thereof including PV modules and the installation thereof must comply with all applicable quality standards, including the standards of the International Electrotechnical Commission set forth in Schedules 2 and 5, and, prior to the occurrence of the Commercial Operations Date, the Seller shall provide certificates of the EPC Contractor and the Engineer confirming that the quality, design, installation and construction of the Complex and the components thereof are in compliance with and satisfy the quality, design and safety standards of the IEC Standards stated in Schedules 2 and 5. (e) The Seller shall ensure that the Complex has adequate security and surveillance equipment and facilities, including a satisfactory security fence around the Complex, so as to minimize the risk of vandalism and theft on the Site, with adequate, trained and experienced personnel available to operate such equipment and to take reasonable action to protect the Complex in the event of any breach or attempted breach of such security equipment and facilities and unauthorized trespass onto the Site.
Appears in 1 contract
Sources: Energy Purchase Agreement
Construction of the Complex. (a) The Seller shall commence and proceed with the construction works of the Complex EPC Works as soon as reasonably practicable following the Effective Date. The Seller shall ensure that the design of the construction works EPC Works shall be carried out with all proper skill, diligence and care and in all material respects in accordance with this Agreement, including the Specifications, the Laws of Pakistan (including the Seller Consents and the Generation Licence), Prudent Utility Practices and Prudent Electrical Practices, so that the Complex is reasonably expected to provide a useful life of not less than the Term.
(b) The Seller shall carry out and complete the construction works Construction Works such that the Seller is able to achieve the Commercial Operations Date in any case no later than the Required Commercial Operations Date.
(c) The Seller shall ensure and shall procure that the Engineer certifies to the Purchaser before the Commissioning Tests that all equipment permanently installed as part of the Complex is new new, contemporary and unused at the time of such installation, and complies with the requirements of Schedules Schedule 2 and Schedule 5.
(d) The Complex and the components thereof including PV modules and WTGs, and the installation thereof must comply with all applicable quality standards, including the standards of the International Electrotechnical Commission set forth in Schedules Schedule 2 and Schedule 5, and, prior to the occurrence of the Commercial Operations Date, the Seller shall provide certificates of the EPC Contractor and the Engineer confirming that the quality, design, installation and construction of the Complex and the components thereof are in compliance with and satisfy the quality, design and safety standards of the IEC Standards stated in Schedules Schedule 2 and Schedule 5.
(e) The Seller shall ensure that the Complex has adequate security and surveillance equipment and facilities, including a satisfactory security fence around the Complex, so as to minimize the risk of vandalism and theft on the Site, with adequate, trained and experienced personnel available to operate such equipment and to take reasonable action to protect the Complex in the event of any breach or attempted breach of such security equipment and facilities and unauthorized trespass onto the Site.
Appears in 1 contract
Sources: Energy Purchase Agreement