CONSTRUCTION, TESTING AND COMMISSIONING Clause Samples

The 'Construction, Testing and Commissioning' clause defines the obligations and procedures related to building, evaluating, and officially starting up a project or facility. It typically outlines the standards and timelines for construction activities, the requirements for testing systems or equipment to ensure they meet specified criteria, and the steps necessary for formal commissioning, such as inspections or certifications. This clause ensures that the completed work is safe, functional, and compliant with contractual and regulatory requirements, thereby reducing the risk of defects or operational failures after handover.
CONSTRUCTION, TESTING AND COMMISSIONING. Construction Responsibilities of the Company
CONSTRUCTION, TESTING AND COMMISSIONING. 26 5.1. Construction Responsibilities of the Company 26 5.2. Further Responsibilities Related to Construction 27 5.3. Warranties on Design and Construction 27 5.4. Independent Verifier 28 5.5. Design, Drawings and Other Documents 29 5.6. Testing and Commissioning 32 5.7. Performance Security 33 5.8. Liquidated Damages for Delay 34 5.9. Project Milestone Schedule 35 5.10. Discovered Heritage Resources 36 5.11. Financing of Project 37 5.12. Importation of Equipment and Materials 38 6. OPERATION AND MAINTENANCE 38 6.1. Operation and Maintenance Responsibilities 38 6.2. Operating Procedures 39 6.3. Operating Security 41 6.4. Company Staff 41 6.5. Planned Downtime; Maintenance Program and Schedule 41 6.6. Unplanned Downtime 42 6.7. Parties to Cooperate 42 7. SUPPLY OF SERVICES 42 7.1. Supply and Delivery of Services 42 7.2. Service Level and Quality 43 7.3. Quality Assessment 43 7.4. Changes to Service Quality Requirements 43 8. REVENUES AND PAYMENTS 44 8.1. Revenues 44 8.2. Fares 46 8.3. Commercial Development 46 8.4. Concession Fees 46 8.5. Payment Terms 46 8.6. Manner of Payment 46 8.7. Value-­‐added Tax 46
CONSTRUCTION, TESTING AND COMMISSIONING. 5.1. Construction of New Facilities a) The Operator shall commence the design and construction of the New Facilities within 15 days of the Effective Date. The Operator shall then proceed with construction of the New Facilities with due expedition and without delay. b) The Facilities shall have passed the Performance Tests by the Time for Completion. c) The Operator is entitled to an extension of the Time for Completion if he is or will be delayed either before or after the Time for Completion by any of the following causes: i) a change in the Specifications for the New Facilities that delays materially the Time for Completion set out in Schedule 2; ii) a Force Majeure event (as defined in Section 11); iii) physical conditions or circumstances on the site for the New Facilities, which are adverse and were not (by the Effective Date) drawn to the Operator’s attention or within its knowledge (as is evidenced by written records) or foreseeable from the data supplied to the Operator by the Authority;
CONSTRUCTION, TESTING AND COMMISSIONING. 26 6. OPERATION AND MAINTENANCE 38 7. SUPPLY OF SERVICES 42 8. REVENUES AND PAYMENTS 44
CONSTRUCTION, TESTING AND COMMISSIONING 

Related to CONSTRUCTION, TESTING AND COMMISSIONING

  • Evaluation, Testing, and Monitoring 1. The System Agency may review, test, evaluate and monitor Grantee’s Products and services, as well as associated documentation and technical support for compliance with the Accessibility Standards. Review, testing, evaluation and monitoring may be conducted before and after the award of a contract. Testing and monitoring may include user acceptance testing. Neither the review, testing (including acceptance testing), evaluation or monitoring of any Product or service, nor the absence of review, testing, evaluation or monitoring, will result in a waiver of the State’s right to contest the Grantee’s assertion of compliance with the Accessibility Standards. 2. Grantee agrees to cooperate fully and provide the System Agency and its representatives timely access to Products, records, and other items and information needed to conduct such review, evaluation, testing, and monitoring.

  • Synchronization, Commissioning and Commercial Operation 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/ and checking/verification is made by the concerned authorities of the PGVCL. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject in-firm power to grid from time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date of execution of this PPA. Declaration of COD shall be certified by the commissioning committee. 5.1.6 The Parties agree that for the purpose of commencement of the supply of electricity by SPG to PGVCL, liquidated damages for delay etc., the Scheduled Commissioning Date as defined in this Agreement shall be the relevant date.

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Post-Commercial Operation Date Testing and Modifications Developer and Connecting Transmission Owner shall each at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice and Applicable Reliability Standards as may be necessary to ensure the continued interconnection of the Large Generating Facility with the New York State Transmission System in a safe and reliable manner. Developer and Connecting Transmission Owner shall each have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Installation, Maintenance, Testing and Repair Unless otherwise agreed in writing by the Parties, to the extent required by Applicable Law, Interconnection provided by a Party shall be equal in quality to that provided by such Party to itself, any subsidiary, affiliates or third party. If either Party is unable to fulfill its obligations under this Section 14.2, it shall notify the other Party of its inability to do so and will negotiate alternative intervals in good faith. The Parties agree that to the extent required by Applicable Law, the standards to be used by a Party for isolating and clearing any disconnections and/or other outages or troubles shall be at parity with standards used by such Party with respect to itself, any subsidiary, affiliate or third party.