Common use of Contingency within the Schedule Clause in Contracts

Contingency within the Schedule. Any contingency within the schedule, i.e. a difference in time between the project's early completion and required contract completion date, and "float" in the approved CPM construction schedule belongs to the project and not to any party to the contract.

Appears in 5 contracts

Sources: Addendum, Addendum to the Standard Specifications, Addendum to the Standard Specifications

Contingency within the Schedule. Any contingency within the scheduleSchedule, i.e. a difference in time between the project's early completion and required contract completion date, and "float" in the approved CPM construction schedule Construction Schedule belongs to the project and not to any party to the contract.

Appears in 2 contracts

Sources: Addendum, Addendum