CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; and
Appears in 16 contracts
Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Standard Form of Agreement Between Owner and Construction Manager as Constructor, Guaranteed Maximum Price Amendment
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work Subcontractor agrees that this Subcontract is assigned by the Contractor to the Owner, Owner provided that .1 that: 1) the assignment is effective only after termination of the Owner/Contractor Contract by the Owner for cause pursuant to Section 14.2 cause, and only for those subcontract agreements that 2) the Owner accepts by notifying notifies the Subcontractor and Contractor; andContractor in writing of the Owner’s exercise of the assignment, and 3) the assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Owner/Contractor Contract.
Appears in 10 contracts
Sources: Subcontract, Subcontract Agreement, Subcontract Agreement
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 6 contracts
Sources: Standard Form of Agreement Between Owner and Contractor, Subcontractor Compliance Agreement, Project Manual
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract subcontract, purchase order and similar agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontracts, purchase orders and similar subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 5 contracts
Sources: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Contractor
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § §5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that that: .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the which Owner accepts by notifying the Subcontractor subcontractor and ContractorContractor in writing; and
Appears in 2 contracts
Sources: Services Agreement, Services Agreement
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 65 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, Owner provided that that:
.1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; andParagraphs 14.2,
Appears in 2 contracts
Sources: General Conditions of the Contract for Construction, General Conditions of the Contract for Construction
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is hereby assigned by the Contractor to the Owner, Owner provided that that: .1 such assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 Article 13, and only for those subcontract agreements that which the Owner accepts by notifying the Subcontractor and Contractorin writing; and
Appears in 2 contracts
Sources: Construction Agreement, Construction Agreement
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract 4.5.1 The Contractor hereby assigns its agreement for a portion of the Work is assigned by the Contractor with each Subcontractor to the Owner, Contracting Authority provided that .1 the assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 Contracting Authority and only for those subcontract agreements that whichthat the Owner Contracting Authority accepts by notifying the Contractor and applicable Subcontractor and Contractor; andin writing. The Contracting Authority may re-assign accepted agreements.
Appears in 2 contracts
Sources: General Contracting Agreement, Standard Requirements for Public Facility Construction
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, Owner provided that .1 assignment that:
(1) Assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 or for convenience and only for those subcontract agreements that the which Owner accepts by notifying the Subcontractor and Contractorcontractor or subcontractor in writing; and
(2) Assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.
Appears in 1 contract
Sources: Subcontract Agreement
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 Article 14 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect (Nu Skin Enterprises Inc)
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a any unperformed portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause or convenience pursuant to Section 14.2 Article 14 or abandonment of the Project by the Contractor and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, Owner provided that that:
.1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section Paragraph 14.2 and only for those subcontract agreements that which the Owner accepts by notifying the Subcontractor and Contractorin writing; and
.2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.
Appears in 1 contract
Sources: Standard Form of Agreement (Windsor Woodmont Black Hawk Resort Corp)
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, Owner provided that .1 assignment that:
5.4.1. Assignment is effective only after termination of the Contract this Agreement with Contractor by the Owner for cause pursuant to Section 14.2 Article 13 of Exhibit A and only for those subcontract agreements that the which Owner accepts by notifying the Subcontractor and Contractorin writing; and
5.4.2. Assignment is subject to the prior rights of the surety, if any, obligated under any bond relating to this Agreement.
Appears in 1 contract
Sources: Energy Services Agreement
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract 4.5.1 The Contractor hereby assigns its agreement for a portion of the Work is assigned by the Contractor with each Subcontractor to the Owner, Contracting Authority provided that .1 the assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 Contracting Authority and only for those subcontract agreements that the Owner Contracting Authority accepts by notifying the Contractor and applicable Subcontractor and Contractor; andin writing. The Contracting Authority may re-assign accepted agreements.
Appears in 1 contract
Sources: Standard Requirements for Public Facility Construction
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; and
Appears in 1 contract
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; and;
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a any unperformed portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause or convenience pursuant to Section 14.2 Article 14 or abandonment of the Project by the Contractor; and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 11.6.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and ContractorContractor in writing; and
Appears in 1 contract
Sources: Standard Abbreviated Form of Agreement Between Owner and Contractor
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, provided that .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section 14.2 and only for those subcontract agreements that the Owner accepts by notifying the Subcontractor and Contractor; andSection
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
CONTINGENT ASSIGNMENT OF SUBCONTRACTS. § 5.4.1 [Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner, Owner provided that that:
.1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Section Paragraph 14.2 and only for those subcontract agreements that which the Owner accepts by notifying the Subcontractor and Contractorin writing; and
.2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.]
Appears in 1 contract