CONTRACT CEILING PRICE. 26.1 If at any time the Subcontractor has reason to believe that an increase in the ceiling of a time and material, unit price or cost reimbursable contract will be necessary, it shall give to Savcor ART prompt notice to that effect, and provide a written estimate to complete the Works and propose a new limitation figure and give appropriate supporting data so that Savcor ART may, in its sole discretion, increase such limitation by written variation to this Agreement. 26.2 The Subcontractor shall not otherwise be entitled to claim any amount which exceeds the ceiling price. 26.3 Any claimed change in the ceiling price shall be dealt with as a claim for costs associated with a Change under Part 15. 26.4 In the event of a dispute arising in relation to the ceiling price, the dispute shall be resolved in accordance with Part 39, and the Subcontractor must continue to perform the Works pending resolution of the dispute.