CONTRACT CONTROVERSIES Clause Samples

The Contract Controversies clause defines the procedures for resolving disputes or disagreements that arise under the contract. Typically, it outlines steps such as negotiation, mediation, or arbitration before parties can pursue litigation, and may specify timelines or required documentation for raising a dispute. This clause ensures that both parties have a clear, agreed-upon process for addressing conflicts, thereby minimizing uncertainty and reducing the risk of prolonged or costly legal battles.
POPULAR SAMPLE Copied 12 times
CONTRACT CONTROVERSIES a. In the event of a controversy or claim arising from this Contract, the Contractor must, within six (6) months after the cause of action occurs, file a written claim with the Contracting Officer for a determination, stating all grounds upon which the Contractor asserts a controversy or claim. The written claim shall state all grounds upon which the Contractor asserts a controversy exists. If the Contractor fails to file a claim or files an untimely claim, the Contractor is deemed to have waived its right to assert a claim in any forum. At the time the claim is filed, or within sixty (60) days thereafter, either party may request mediation through the Commonwealth of Pennsylvania’s Office of General Counsel Mediation Program. b. If the Contractor or the Contracting Officer requests mediation and the other party agrees, the Contracting Officer shall promptly make arrangements for mediation. Mediation shall be scheduled so as to not delay the issuance of the final determination beyond the required 120 days after receipt of the claim if mediation is unsuccessful. c. If mediation is not agreed to or if resolution is not reached through mediation, the Contracting Officer shall review timely filed claims and issue a final determination, in writing, regarding the claim. The final determination shall be issued within 120 days of the receipt of the claim, unless extended by consent of the Contracting Officer and the Contractor. The Contracting Officer shall send his/her written determination to the Contractor. If the Contracting Officer fails to issue a final determination within the 120 days (unless extended by consent of the parties), the claim shall be deemed denied. The Contracting Officer's determination shall be the final order of the purchasing agency. d. Within fifteen (15) days of the mailing date of the determination denying a claim or within 135 days of filing a claim if no extension is agreed to by the parties, whichever occurs first, the Contractor may file a statement of claim with the Commonwealth Board of Claims. Pending a final judicial resolution of a controversy or claim, the Contractor shall proceed diligently with the performance of this Contract in a manner consistent with the determination of the Contracting Officer and the University shall compensate the Contractor pursuant to the terms of this Contract.
CONTRACT CONTROVERSIES. All claims, disputes or other matters which cannot be disposed of by mutual agreement, shall be settled in accordance with Alaska Statute 36.30.620 through 36.30.699 of the Procurement Code.
CONTRACT CONTROVERSIES a. In the event of a controversy or claim arising from the Contract, the Contractor must, within six months after the cause of action accrues, file a written notice of controversy or claim with the Contracting Officer for a determination. The claim shall state all grounds upon which the Contractor asserts a controversy exists. If the Contractor fails to file a claim or files an untimely claim, the Contractor is deemed to have waived its right to assert a claim in any forum. b. The contracting officer shall review timely filed claims and issue a final determination, in writing, regarding the claim. The final determination shall be issued within 120 days of the receipt of the claim, unless extended by consent of the Contracting Officer and the Contractor. The Contracting Officer shall send his/her written determination to the Contractor. If the Contracting Officer fails to issue a final determination within the 120 days (unless extended by consent of the Parties), the claim shall be deemed denied. The contracting officer’s determination shall be the final order of the Purchasing Agency. c. Within fifteen (15) days of the mailing date of the determination denying a claim or within 135 days of filing a claim if, no extension is agreed to by the parties, whichever occurs first, the Contractor may file a statement of claim with the Commonwealth Board of Claims. Pending a final judicial resolution of a controversy or claim, the Contractor shall proceed diligently with the performance of the Contract in a manner consistent with the determination of the Contracting Officer and the Commonwealth shall compensate the Contractor pursuant to the terms of the Contract.
CONTRACT CONTROVERSIES. In the event of a controversy or claim arising from the Contract, the Contractor must, within six months after the cause of action accrues, file a written claim with the contracting officer for a determination. The claim shall state all grounds upon which the Contractor asserts a controversy exists. If the Contractor fails to file a claim or files an untimely claim, the Contractor is deemed to have waived its right to assert a claim in any forum.
CONTRACT CONTROVERSIES. A. In the event of a controversy or claim arising from the Contract, the Contractor must, within six months after the cause of action accrues, file a written claim with the County for a determination. The claim shall state all grounds upon which the Contractor asserts a controversy exists. If the Contractor fails to file a claim or files an untimely claim, the Contractor is deemed to have waived its right to assert a c1aim in any forum. B. The County shall review timely filed claims and issue a final determination in writing regarding the claim. The final determination shall be issued within 120 days of the receipt of the claim, unless extended by consent of the County and the Contractor. The County shall send its written determination to the Contractor. If the County fails to issue a final determination within the 120-day period (unless extended by consent of the parties), the claim shall be deemed denied. The County’s determination shall be its final order. C. Within fifteen 15 days of the mailing date of the determination denying a claim or within 135 days of filing a claim, if no extension is agreed to by the parties, whichever occurs first, the Contractor may file litigation, restricted to non-jury trial, in the Court of Common Pleas of Cumberland County, which venue and jurisdiction shall be exclusive. No claim shall be filed after this time period has expired. Pending a final judicial resolution of a controversy or claim, the Contractor shall proceed diligently with the performance of the Contract in a manner consistent with the determination of the County and the County shall compensate the Contractor pursuant to the terms of the Contract.
CONTRACT CONTROVERSIES. Any claim or controversy arising out of this Participating Addendum, State Contract Number 4400019304, or any order issued pursuant to State Contract Number 4400019304, shall be resolved by the provisions of Louisiana Revised Statute 39:1673.
CONTRACT CONTROVERSIES. In the event of a controversy or claim between the Law Firm and the Board arising from this Contract, the Law Firm must, within six months after the cause of action accrues, file a written notice of the controversy or claim with the Chief Counsel for a determination. The Chief Counsel shall send a written determination to the Law Firm within 60 days of receipt of such written notice. The decision of the Chief Counsel shall be final and conclusive unless, within 15 days after receipt of such written determination, the Law Firm files a claim with the Commonwealth of Pennsylvania Board of Claims ("Board of Claims"). Pending a final judicial resolution of a controversy or claim, the Law Firm shall proceed diligently with the performance of this Contract in a manner consistent with the interpretation of the Board, and the Board shall continue to compensate the Law Firm pursuant to the terms of this Contract.
CONTRACT CONTROVERSIES. Any claim or controversy arising out of the Contract shall be resolved by the provisions of Louisiana Revised Statute 39:1524-26.
CONTRACT CONTROVERSIES 

Related to CONTRACT CONTROVERSIES

  • Controversies (a) Buyer shall notify Seller in writing within ten (10) days of the receipt by Buyer or the Acquired Company of written notice of any inquiries, audits, examinations, assessments or other proceedings from any Taxing Authority with respect to Taxes of the Acquired Company for which Seller would be required to indemnify any Buyer Indemnitee pursuant to this Agreement (any such inquiry, audit, examination, assessment or similar event, a "Tax Matter"); provided, however that any failure by ▇▇▇▇▇ to deliver such notice within such time period shall not affect in any way Seller's obligation for indemnification, except if and to the extent Seller is actually and materially prejudiced thereby. Seller may, at Seller's own expense, participate in and, upon notice to ▇▇▇▇▇, assume the defense of any such Tax Matter relating solely to a Tax period ending on or before the Closing Date (b) Buyer has the right to represent the interests of the Acquired Company before the relevant Taxing Authority with respect to any inquiry, audit, examination, assessment or proceeding relating to a Straddle Period (a "Straddle Period Tax Matter") and has the right to control the defense, compromise or other resolution of any such Straddle Period Tax Matter, including responding to inquiries, filing Tax Returns and contesting, defending against and resolving any assessment for additional Taxes or notice of Tax deficiency or other adjustment of Taxes of, or relating to, such Straddle Period Tax Matter. If Seller would be required to indemnify any Buyer Indemnitee pursuant to this Agreement with respect to such Straddle Period Tax Matter then (i) Seller shall have the right (but not the duty) to participate in the defense of such Straddle Period Tax Matter and to employ counsel, at Seller's own expense, separate from counsel employed by Buyer, (ii) Buyer shall not enter into any settlement of or otherwise compromise any such Straddle Period Tax Matter to the extent that it adversely affects the Tax liability of Seller or results in an indemnity obligation under this Agreement without the prior written consent of Seller, which consent shall not be unreasonably withheld, conditioned or delayed, and (iii) Buyer shall keep Seller informed with respect to the commencement, status and nature of any such Straddle Period Tax Matter, and will, in good faith, allow Seller or Seller's counsel to consult with Buyer or its counsel regarding the conduct of or positions taken in any such proceeding and to be present at any meetings or proceedings with the relevant Taxing Authority.

  • Disputes In the case of a dispute as to the determination of the Exercise Price or the arithmetic calculation of the number of Warrant Shares issuable in connection with any exercise, the Company shall promptly deliver to the Holder the number of Warrant Shares that are not disputed.