Contract Maximum. The maximum amount payable each year to the County from the District under this Agreement is the Final Estimated Cost described in Section 3.1 above plus an additional contingency charge of 10 percent of the Materials Estimate. The County shall not undertake work on the District's Projects when such work is expected to exceed this Contract Maximum absent first obtaining written approval from the District.
Appears in 2 contracts
Sources: Interlocal Agreement, Interlocal Agreement
Contract Maximum. The maximum amount payable each year to the County from the District under this Agreement is the Final Estimated Cost described in Section 3.1 above plus an additional contingency charge of 10 percent of the Materials Estimate. The County shall not undertake work on the District's ’s Projects when such work is expected to exceed this Contract Maximum absent first obtaining written approval from the District.
Appears in 1 contract
Sources: Interlocal Agreement