Common use of Contract Times Clause in Contracts

Contract Times. Dates A. The Work will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before , and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before [date], and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024[date].

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before June 1, 2026 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before , and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024.before

Appears in 2 contracts

Sources: Construction Contract, Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before (Date), and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024(Date).

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before _June 1, 2019_, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions Conditions, as applicable, on or before 5/31/2024_July 16, 2019_. B. Parts of the Work shall be substantially completed on or before the following Milestone(s): 1. Milestone 1 [N/A]

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before September 26, 2025 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before August 26, 2024 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before November 15, 2023, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024November 30, 2023.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially complete completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions based on or before 5/31/2024the issue date of the Notice To Proceed.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before September 6, 2019, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024September 20, 2019.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before August 29, 2025 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before January 31, 2025, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024February 28, 2025.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before August 1, 2025 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before October 25, 2024 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before October 13, 2023, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024October 20, 2023.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before November 15, 2024 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before _July 31, 2019 , and completed and ready for final payment in accordance with Paragraph 15.06 of the Standard General Conditions on or before 5/31/2024August 15, 2019 _.

Appears in 1 contract

Sources: Construction Contract

Contract Times. DatesDates (not applicable) A. The Work will be substantially complete on or before [date], and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024[date].

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially complete on or before [date], and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024.[date]. [OR]

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024Conditions.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before October 15, 2023 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract

Contract Times. Dates A. The Work will be substantially completed on or before August 30, 2024 and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before 5/31/2024the 14th day following substantial completion.

Appears in 1 contract

Sources: Construction Contract