Contract Times. The Work shall be substantially completed within 5 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 Calendar Days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Contract Times. The Work shall be substantially completed within 5 54 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 54 Calendar Days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Contract Times. The Work shall be substantially completed within 5 Calendar Days 60 calendar days after the date when specified in the Contract Time commences Notice to run. The Work shall be Proceed (“Substantial Completion”), and completed and ready for final payment, payment in accordance with the General Conditions, Contract Documents within 5 Calendar Days 30 calendar days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated specified in the Notice to ProceedProceed (“Final Completion”).
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Contract Times. The 2.1 CONTRACTOR shall achieve Substantial Completion of the Work shall be substantially completed within 5 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 Calendar Days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 1 contract
Sources: Construction Contract
Contract Times. The Work shall be substantially completed within 5 29 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 40 Calendar Days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 1 contract
Sources: Construction Agreement
Contract Times. The Work shall be substantially completed within 5 12 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 12 Calendar Days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 1 contract
Sources: Construction Contract
Contract Times. 3.1 The Work shall will be substantially completed within 5 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 Calendar Days 210 calendar days after the date when the Contract Times commence to run. The , and completed and ready for final payment within 240 calendar days after the date when the Contract Times shall commence to run on the day indicated in the Notice to Proceedrun.
Appears in 1 contract
Sources: Construction Contract
Contract Times. 3.1 The Work work shall be substantially completed complete within 5 Calendar Days 365 calendar days after the date when the Contract Time commences Times commence to runrun as provided in Section 5.6 of the Invitation to Bid. The Work work shall be completed and ready for final payment, payment in accordance with Section 5.11.4 of the General Conditions, Invitation to Bid within 5 Calendar Days 405 calendar days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.\
Appears in 1 contract
Sources: Standard Form of Agreement
Contract Times. The Work shall will be substantially completed within 5 Calendar Days 25 calendar days after the date when the Contract Time commences Times commence to run. The Work shall be run as provided in General Conditions Paragraph 2.03 as amended by the Supplementary Conditions, and completed and ready for final payment, payment in accordance with Paragraph 14.07 of the General Conditions, Conditions within 5 Calendar Days 30 calendar days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 1 contract
Sources: Construction Contract
Contract Times. 3.1. The Work shall will be substantially completed within 5 Calendar Days 90 calendar days after the date when the Contract Time commences Times commence to run. The Work shall be run completed and ready for final payment, payment in accordance with paragraph 14.07 of the General Conditions, Conditions within 5 Calendar Days 120 calendar days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to Proceed.
Appears in 1 contract
Sources: Construction Contract
Contract Times. 3.1 The Work shall will be substantially completed complete and operational within 5 Calendar Days 270 calendar days after the date when the Contract Time commences to run. The Work shall be run and completed and ready for final payment, in accordance with the General Conditions, payment within 5 Calendar Days 30 days after the date when the Contract Times commence to run. The Contract Times shall commence to run on the day indicated in the Notice to ProceedSubstantial Completion.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor on the Basis of a Stipulated Price
Contract Times. 3.1 The Work shall will be substantially completed within 5 Calendar Days after the date when the Contract Time commences to run. The Work shall be completed and ready for final payment, in accordance with the General Conditions, within 5 Calendar Days 280 calendar days after the date when the Contract Times commence to run. The , and completed and ready for final payment within 310 calendar days after the date when the Contract Times shall commence to run on the day indicated in the Notice to Proceedrun.
Appears in 1 contract
Sources: Construction Contract