Contractor Initiated Changes (Claims). A. Weather Days. If Contractor is not able to work on a critical path or controlling item on the Project for at least half of a regular scheduled work day because of inclement weather, then the Contractor shall be entitled to adjustments in the Contract Time. Adjustments to the Contract Time are calculated for each weather day that is greater than the anticipated number of weather days for the given month as shown below: January 8 February 8 March 7 May 4 June 3 July 2 August 2 September 2 October 4 November 5 December 7