Common use of Contractor Obligation to Mitigate Delay Clause in Contracts

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 and 6.8, in no event shall Contractor be entitled to any adjustment to the Key Dates or adjustment to the Contract Price for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurred.

Appears in 3 contracts

Sources: Fixed Price Turnkey Agreement (NextDecade Corp.), Fixed Price Turnkey Agreement (NextDecade Corp.), Fixed Price Turnkey Agreement (NextDecade Corp.)

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 6.6 and 6.8, in no event shall Contractor be entitled to any adjustment to the Key Dates Project Schedule or adjustment to the Estimated Contract Price for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurreddelay.

Appears in 3 contracts

Sources: Construction Agreement (Cheniere Energy Inc), Construction Agreement (Cheniere Energy Inc), Construction Agreement (Cheniere Energy Inc)

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 6.8 and 6.86.9, in no event shall Contractor be entitled to any adjustment to the Key Dates Guaranteed Mechanical Completion Date or adjustment to the Contract Price Project Schedule for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurreddelay.

Appears in 2 contracts

Sources: Construction Agreement (Cheniere Corpus Christi Holdings, LLC), Construction Agreement (Cheniere Corpus Christi Holdings, LLC)

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 and 6.8, in no event shall Contractor be entitled to any adjustment to the Key Dates or adjustment to the Contract Price for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurred.. 6.11

Appears in 2 contracts

Sources: Fixed Price Turnkey Agreement (NextDecade Corp), Epc Agreement (NextDecade Corp)

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 and 6.8, in no event shall Contractor be entitled to any adjustment to the Key Milestone Dates or any adjustment to the Contract Guaranteed Maximum Price for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurreddelay.

Appears in 2 contracts

Sources: Turnkey Agreement (Global Clean Energy Holdings, Inc.), Turnkey Agreement (Global Clean Energy Holdings, Inc.)

Contractor Obligation to Mitigate Delay. With respect to Sections 6.7 and 6.8, in no event shall Contractor be entitled to any adjustment to the Key Guaranteed Dates or adjustment to the Contract Price for (i) that portion of delay to the extent Contractor could have taken, but failed to take, reasonable actions to mitigate such delay or (ii) that portion of delay that would nevertheless been experienced had such delay event in Section 6.7 or 6.8 not occurreddelay.

Appears in 1 contract

Sources: Fixed Price Separated Turnkey Agreement (Cheniere Energy, Inc.)