Common use of Contractor's Progress Reports Clause in Contracts

Contractor's Progress Reports. The Contractor shall submit Monthly and Quarterly Progress Reports to the Engineer in quadruplicate at least 7 days prior to the date of monthly and quarterly progress meeting. The actual work done shall be superimposed upon the copies of the programme. He shall furnish an explanation of any deviation from the programme, and shall state proposals for improving progress, should this be lacking in any respect.

Appears in 3 contracts

Sources: Construction Contract, Construction Contract, Construction Contract