Cooperation and assistance on transfer of Project. 32.3.1 The Parties shall cooperate on a best efforts basis and take all necessary measures, in good faith, to achieve a smooth transfer of the Project in accordance with the provisions of this Agreement so as to protect the safety of and avoid undue delay or inconvenience to the Users, other members of the public or the lawful occupiers of any part of the Site. 32.3.2 The Parties shall provide to each other, 9 (nine) months prior to the Transfer Date in the event of Termination by efflux of time and immediately in the event of either Party conveying to the other Party its intent to issue a Termination Notice, as the case may be, as much information and advice as is reasonably practicable regarding the proposed arrangements for operation of the Project following the Transfer Date. The Concessionaire shall further provide such reasonable advice and assistance as the Authority, its Concessionaire or agent may reasonably require for operation of the Project until the expiry of 6 (six) months after the Transfer Date. 32.3.3 The Authority shall have the option to purchase or hire from the Concessionaire at a fair market value and free from any encumbrance all or any part of the plant and machinery used in connection with the Project but which does not form part of the assets specified in Clause 32.1.1 and is reasonably required in connection with operation of the Project. For the avoidance of doubt, in the event of dispute or difference relating to fair market value, the Dispute Resolution Procedure as set out under Clause 37.1 shall apply. 32.3.4 The Authority reserves the right to invite bids for the Project at an appropriate time before expiry of Concession Period to enable smooth transition. The Concessionaire reserves the right to bid. The Authority reserves the right to amend the bid conditions, scope of work etc. while inviting fresh bids. The Concessionaire shall allow the core team (consisting of maximum of four persons) of the successful bidder the fresh bid(s) to enter the premises 7 (seven) days before expiry of Concession Period to monitor work and take charge at the appointed hour. 32.3.5 During re-bidding of the Project, the Concessionaire shall have the first right of refusal, subject to the following:
Appears in 1 contract
Sources: Concession Agreement
Cooperation and assistance on transfer of Project. 32.3.1 The Parties shall cooperate on a best efforts basis and take all necessary measures, in good faith, to achieve a smooth transfer of the Project in accordance with the provisions of this Agreement so as to protect the safety of and avoid undue delay or inconvenience to the Users, other members of the public or the lawful occupiers of any part of the Site.
32.3.2 The Parties shall provide to each other, 9 (nine) months prior to the Transfer Date in the event of Termination by efflux of time and immediately in the event of either Party conveying to the other Party its intent to issue a Termination Notice, as the case may be, as much information and advice as is reasonably practicable regarding the proposed arrangements for operation of the Project following the Transfer Date. The Concessionaire shall further provide such reasonable advice and assistance as the Authority, its Concessionaire or agent may reasonably require for operation of the Project until the expiry of 6 (six) months after the Transfer Date.
32.3.3 The Authority shall have the option to purchase or hire from the Concessionaire at a fair market value and free from any encumbrance all or any part of the plant and machinery used in connection with the Project but which does not form part of the assets specified in Clause 32.1.1 and is reasonably required in connection with operation of the Project. For the avoidance of doubt, in the event of dispute or difference relating to fair market value, the Dispute Resolution Procedure as set out under Clause 37.1 shall apply.
32.3.4 The Authority reserves the right to invite bids for the Project at an appropriate time before expiry of Concession Period to enable smooth transition. The Concessionaire reserves the right to bid. The Authority reserves the right to amend the bid conditions, scope of work etc. while inviting fresh bids. The Concessionaire shall allow the core team (consisting of maximum of four persons) of the such successful bidder the fresh bid(s) to enter the premises 7 (seven) days before expiry of Concession Period to monitor work and take charge at the appointed hour.
32.3.5 During re-bidding of the Project, the Concessionaire shall have the first right of refusal, subject to the following:
(a) The Concessionaire shall participate in the re-bid of the Project;
(b) The Authority shall reserve the right to modify existing or introduce new terms and conditions and bid parameters; and
(c) The Concessionaire shall have a right to match the highest bid to exercise the first right of refusal if its bid is within the range of 10% (ten per cent) of the most competitive bid received.
Appears in 1 contract
Sources: Concession Agreement