Coordination and Cooperation. 1The Parties hereby acknowledge that the timely completion of each Transit Project will be influenced by the ability of MTA and Utility to coordinate their activities, communicate with each other, and respond promptly to reasonable requests. As information becomes available for each Transit Project, MTA will promptly provide to Utility such plans for the Project as will enable Utility to determine which Utility Facilities may be impacted thereby. The Parties will endeavor to agree on the plans and specifications for each arrangement prior to the giving of formal notice to Utility of a required Rearrangement. This Section 1.5.1 is directory only and compliance therewith or agreement upon plans and specifications as aforesaid shall not be a condition precedent to the giving of formal notice to Utility of a required Rearrangement.
Appears in 3 contracts
Sources: Utility Cooperative Agreement, Utility Cooperative Agreement, Utility Cooperative Agreement