Correction Period. A. For a period of one (1) year from the date of Substantial Completion of the Work or a designated portion thereof, unless otherwise stated in Substantial Completion Notice(s) from OWNER, the Contractor shall remedy at the Contractor’s expense any failure to conform to the Contract requirements or any defect. B. The Contractor shall remedy at the Contractor’s expense any damage to real or personal property owned or controlled by the OWNER, when the damage is the result of: 1. Contractor’s failure to conform to Contract requirements; or 2. Any defect of equipment, material, workmanship, or design furnished. C. The Contractor shall restore any Work damaged in fulfilling the terms and conditions of this Article. The Contractor warranty with respect to work repaired or replaced shall run for one year from the date of repair or replacement. D. The OWNER shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. E. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the OWNER shall have the right to replace, remove, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
Appears in 9 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Correction Period.
A. For a period of one (1) year from the date of Substantial Completion of the Work or a designated portion thereof, unless otherwise stated in Substantial Completion Notice(s) from OWNER, the Contractor shall remedy at the Contractor’s expense any failure to conform to the Contract requirements or any defect.
B. The Contractor shall remedy at the Contractor’s expense any damage to real or personal property owned or controlled by the OWNER, when the damage is the result of:
1. Contractor’s failure to conform to Contract requirements; or
2. Any defect of equipment, material, workmanship, or design furnished.
C. The Contractor shall restore any Work damaged in fulfilling the terms and conditions of this Article. The Contractor warranty with respect to work repaired or replaced shall run for one year from the date of repair or replacement.
D. The OWNER shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
E. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the OWNER shall have the right to replace, remove, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
Appears in 6 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Correction Period. A. For a period of one (1) year from the date of Substantial Completion of the Work or a designated portion thereof, unless otherwise stated in Substantial Completion Notice(s) from OWNER, the Contractor shall remedy at the Contractor’s expense any failure to conform to the Contract requirements or any defect.
B. The Contractor shall remedy at the Contractor’s expense any damage to real or personal property CONSTRUCTION CONTRACT ` SPECIAL PROVISIONS owned or controlled by the OWNER, when the damage is the result of:
1. Contractor’s failure to conform to Contract requirements; or
2. Any defect of equipment, material, workmanship, or design furnished.
C. The Contractor shall restore any Work damaged in fulfilling the terms and conditions of this Article. The Contractor warranty with respect to work repaired or replaced shall run for one year from the date of repair or replacement.
D. The OWNER shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
E. If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the OWNER shall have the right to replace, remove, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
Appears in 1 contract
Sources: Construction Contract