Cost of Change Orders. 7.7.1 Scope Within ten (10) calendar days or such lesser period of time as may be required by District after a request is made for a change that impacts the Contract Sum or the Contract Time, the Contractor shall provide to the District and the Architect in writing an estimate of the effect of the proposed CO upon the Contract Price and the actual cost of construction, which shall include a complete itemized cost breakdown of all labor and material showing actual quantities, hours, unit prices, wage rates, required for the change, and the effect upon the Contract Time of such CO. Changes may be made by District by an appropriate written CO, or, at the District’s option, such changes shall be implemented immediately upon the Contractor’s receipt of an appropriate written CCD.