Cost of Remedying Defetcts. All work referred to in sub-paragraph (b) of Sub-Clause 11.1 [Completion of Outstanding Work and Remedying Defects] shall be executed at the risk and cost of the Contractor, if and to the extent that work is attributable to: (a) the design of the Works other than a part of the design for which the Employer is responsible (if any), (b) Plant, Materials or workmanship not being in accordance with the Contract, 34 Conditions of Contract for Plant and Design-Build (c) improper operation or maintenance which was attributable to matters for which the Contractor is responsible (under Sub-Clauses 5.5 to 5.7 or otherwise), or (d) failure by the Contractor to comply with any other obligation.