COSTS EXCLUDED FROM COST OF WORK. The following shall not be included in the Cost of the Work: 10.1.1 Salaries and other compensation of the CM/GC's personnel stationed at the CM/GC's principal office or offices other than the site office except as allowed under Articles 9.2.2 and 9.2.3. 10.1.2 Expenses of the CM/GC's principal office and offices other than the site office. 10.1.3 Any overhead and general expenses, except as may be expressly included in Article 9. 10.1.4 CM/GC's capital expenses, including interest on the CM/GC's capital employed for the Work. 10.1.5 Rental cost of machinery and equipment, except as provided in Article 9.5.2 10.1.6 Any cost associated with the Project not specifically and expressly described in Article 9. 10.1.7 Costs due to the fault or negligence of the CM/GC, Subcontractors, suppliers, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable. 10.1.8 The cost of correction of any repair work, nonconforming or defective work, or warranty work. 10.1.9 Merit, safety, or other incentive payments, bonuses or awards, or any expenses in connection therewith, except as provided in Article 9.6.5.
Appears in 3 contracts
Sources: Cm/Gc Contract, Construction Manager/General Contractor Contract, Cm/Gc Contract
COSTS EXCLUDED FROM COST OF WORK. The following shall not be included in the Cost of the Work:
10.1.1 9.1.1 Salaries and other compensation of the CM/GC's personnel stationed at the CM/GC's principal office or offices other than the site office except as allowed under Articles 9.2.2 8.2.2 and 9.2.38.2.3.
10.1.2 9.1.2 Expenses of the CM/GC's principal office and offices other than the site office.
10.1.3 9.1.3 Any overhead and general expenses, except as may be expressly included in Article 98.
10.1.4 9.1.4 CM/GC's capital expenses, including interest on the CM/GC's capital employed for the Work.
10.1.5 9.1.5 Rental cost of machinery and equipment, except as provided in Article 9.5.28.5.2
10.1.6 9.1.6 Any cost associated with the Project not specifically and expressly described in Article 98.
10.1.7 9.1.7 Costs due to the fault or negligence of the CM/GC, Subcontractors, suppliers, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable.
10.1.8 9.1.8 The cost of correction of any repair work, nonconforming or defective work, or warranty work.
10.1.9 9.1.9 Merit, safety, or other incentive payments, bonuses or awards, or any expenses in connection therewith, except as provided in Article 9.6.58.6.5.
Appears in 1 contract
Sources: Cm/Gc Contract
COSTS EXCLUDED FROM COST OF WORK. The following shall not be included in the Cost of the Work:
10.1.1 9.1.1 Salaries and other compensation of the CM/GC's ’s personnel stationed at the CM/GC's ’s principal office or offices other than the site office except as allowed under Articles 9.2.2 8.2.2 and 9.2.38.2.3.
10.1.2 9.1.2 Expenses of the CM/GC's ’s principal office and offices other than the site office.
10.1.3 9.1.3 Any overhead and general expenses, except as may be expressly included in Article 98.
10.1.4 9.1.4 CM/GC's ’s capital expenses, including interest on the CM/GC's ’s capital employed for the Work.
10.1.5 9.1.5 Rental cost of machinery and equipment, except as provided in Article 9.5.28.5.2
10.1.6 9.1.6 Any cost associated with the Project not specifically and expressly described in Article 98.
10.1.7 9.1.7 Costs due to the fault or negligence of the CM/GC, Subcontractors, suppliers, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable.
10.1.8 9.1.8 The cost of correction of any repair work, nonconforming or defective work, work or warranty work.
10.1.9 9.1.9 Merit, safety, or other incentive payments, bonuses or awards, or any expenses in connection therewith, except as provided in Article 9.6.58.
Appears in 1 contract
COSTS EXCLUDED FROM COST OF WORK. The following shall not be included in the Cost of the Work:
10.1.1 9.1.1 Salaries and other compensation of the CM/GC's personnel stationed at the CM/GC's principal office or offices other than the site office except as allowed under Articles 9.2.2 8.2.2 and 9.2.38.2.3.
10.1.2 9.1.2 Expenses of the CM/GC's principal office and offices other than the site office.
10.1.3 9.1.3 Any overhead and general expenses, except as may be expressly included in Article 98.
10.1.4 9.1.4 CM/GC's capital expenses, including interest on the CM/GC's capital employed for the Work.
10.1.5 9.1.5 Rental cost of machinery and equipment, except as provided in Article 9.5.28.5.2
10.1.6 9.1.6 Any cost associated with the Project not specifically and expressly described in Article 98.
10.1.7 9.1.7 Costs due to the fault or negligence of the CM/GC, Subcontractors, suppliers, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable.
10.1.8 9.1.8 The cost of correction of any repair work, nonconforming or defective work, work or warranty work.
10.1.9 9.1.9 Merit, safety, or other incentive payments, bonuses or awards, or any expenses in connection therewith, except as provided in Article 9.6.58.
Appears in 1 contract
Sources: Cm/Gc Contract
COSTS EXCLUDED FROM COST OF WORK. (Not To Be Reimbursed)
9.1 Costs Excluded from Cost of Work. The following shall not be included in the Cost of the Work:
10.1.1 9.1.1 Salaries and other compensation of the CM/GC's personnel stationed at the CM/GC's principal office or offices other than the site office except as allowed under Articles 9.2.2 8.2.2 and 9.2.38.2.3.
10.1.2 9.1.2 Expenses of the CM/GC's principal office and offices other than the site office.
10.1.3 9.1.3 Any overhead and general expenses, except as may be expressly included in Article 98.
10.1.4 9.1.4 CM/GC's capital expenses, including interest on the CM/GC's capital employed for the Work.
10.1.5 9.1.5 Rental cost of machinery and equipment, except as provided in Article 9.5.28.5.2
10.1.6 9.1.6 Any cost associated with the Project not specifically and expressly described in Article 98.
10.1.7 9.1.7 Costs due to the fault or negligence of the CM/GC, Subcontractors, suppliers, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable.anyone
10.1.8 9.1.8 The cost of correction of any repair work, nonconforming or defective work, or warranty work.
10.1.9 9.1.9 Merit, safety, or other incentive payments, bonuses or awards, or any expenses in connection therewith, except as provided in Article 9.6.58.