Common use of Critical Path Analysis Clause in Contracts

Critical Path Analysis. Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on completion of the Work and Contract Time, based on the Work Progress Schedule. Contractor shall include with Time Extension Requests a reasonably detailed narrative setting forth: 12.11.3.1 The nature of the delay and its cause due to a change in the Work or an Excusable Delay and the basis of Contractor’s claim of entitlement to an extension of Contract Time. 12.11.3.2 Documentation of the actual impacts of the claimed delay on the critical path in Contractor’s Work Progress Schedule, and any concurrent delays. 12.11.3.3 Description and documentation of steps taken by Contractor to mitigate the effect of the claimed delay, including, when appropriate, the modification of the Work Progress Schedule.

Appears in 2 contracts

Sources: Construction Manager at Risk Agreement, Professional Services Agreement