Common use of Critical Path Method Clause in Contracts

Critical Path Method. The terms “Critical Path Method” or “CPM” mean a process for building a construction project schedule and analyzing it to determine the most critical tasks that most affect the scheduled completion date. These critical tasks cannot be delayed without changing the overall schedule.

Appears in 6 contracts