Curing and Protection. The brick work shall be kept wet by misting (flooding not allowed) for 7 days commencing from 24 hours after the course is laid. At the end of the day's work the masonry construction shall be protected from harmful effects of rain, sun, and frost by suitable coverings such as tarpaulin or any other suitable coverings. Care shall be taken during construction that edges of jambs, ▇▇▇▇▇, heads etc. are not damaged. CW.6.14. Scaffolding Double scaffolding having two sets of vertical supports shall be provided as directed by the Engineer. The supports shall be sound and strong and of steel tubular construction unless otherwise by other approved means. The vertical posts shall be tied together with horizontal pieces over which the scaffolding planks be fixed. The three sides of the scaffolding should be covered with 1.0m wide plyboards to protect the materials from dropping off while working. Areas having work performed above ground floor shall be segregated for worker safety.
Appears in 3 contracts
Sources: Contract Agreement, Procurement Agreement, Contract Agreement
Curing and Protection. i. The brick work shall be kept wet by misting (flooding not allowed) for 7 days commencing from 24 hours after the course is laid.
ii. At the end of the day's work the masonry construction shall be protected from harmful effects of rain, sun, and frost by suitable coverings such as tarpaulin or any other suitable coverings.
iii. Care shall be taken during construction that edges of jambs, ▇▇▇▇▇, heads etc. are not damaged. CW.6.14. Scaffolding Double scaffolding having two sets of vertical supports shall be provided as directed by the Engineer. The supports shall be sound and strong and of steel tubular construction unless otherwise by other approved means. The vertical posts shall be tied together with horizontal pieces over which the scaffolding planks be fixed. The three sides of the scaffolding should be covered with 1.0m wide plyboards to protect the materials from dropping off while working. Areas having work performed above ground floor shall be segregated for worker safety.
Appears in 1 contract
Sources: Procurement Agreement