Common use of Cut and Fill Slopes Clause in Contracts

Cut and Fill Slopes. Normal fill slopes will be 1½:1 minimum; normal cut slopes will be ½:1, or as determined on a site specific basis by the Timber Sale Officer. In solid rock, and in construction of temporary roads, cut slopes may be steeper. In localized unstable soils, slopes shall be flattened as determined by the Sale Officer, but not to exceed 2:1.

Appears in 6 contracts

Sources: Standard Agreement, Standard Agreement, Standard Agreement

Cut and Fill Slopes. Normal fill slopes will be 1½:1 minimum; normal cut slopes will be ½:1, or as determined on a site site-specific basis by the Timber Sale Officer. In solid rock, and in construction of temporary roads, cut slopes may be steeper. In localized unstable soils, slopes shall be flattened as determined by the Sale Officer, but not to exceed 2:1.

Appears in 1 contract

Sources: Timber Sale Agreement