Daily Log. 2.5.9.1 The CM@Risk shall maintain a daily log of construction activities for each calendar day of the Contract Time, using a form pre-approved by the Design Professional. In that log the CM@Risk shall document all activities at the Work Site, including, but not limited to: a) Weather conditions showing the high and low temperatures during work hours, the amount of precipitation received on the job Site, and any other weather conditions which adversely affect Work at the Site; b) Soil conditions which adversely affect Work at the Site; c) The hours of operation by CM@Risk and individual Subcontractor personnel; d) The number of CM@Risk and Subcontractor personnel present and working at the Site, by subcontract and trade, and updated schedule activity number; e) The equipment active or idle at the Site; f) A description of the Work being performed at the Site by updated schedule activity number; g) Any delays, disruptions or unusual or special occurrences at the Site; h) Materials received at job Site; i) A list of all visitors at the Site; and j) Any other information deemed relevant as to activities on the Site that day. 2.5.9.2 The CM@Risk shall provide copies of the daily logs to the Owner on a weekly basis. The daily log shall not constitute written notice to the Owner of any event or occurrence when such notice is required by the Contract Documents. 2.5.9.3 Any changes affecting previously approved Work shall require prior written approval of the Owner.
Appears in 5 contracts
Sources: Standard Agreement Between Owner and Cm@risk on the Basis of a Guaranteed Maximum Price, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Daily Log. 2.5.9.1 The CM@Risk shall maintain a daily log of construction activities for each calendar day of the Contract Time, using a form pre-approved by the Design Professional. In that log the CM@Risk shall document all activities at the Work Site, including, but not limited to:
a) Weather conditions showing the high and low temperatures during work hours, the amount of precipitation received on the job Site, and any other weather conditions which adversely affect Work at the Site;
b) Soil conditions which adversely affect Work at the Site;
c) The hours of operation by CM@Risk and individual Subcontractor personnel;
d) The number of CM@Risk and Subcontractor personnel present and working at the Site, by subcontract and trade, and updated schedule activity number;
e) The equipment active or idle at the Site;
f) A description of the Work being performed at the Site by updated schedule activity number;
g) Any delays, disruptions or unusual or special occurrences at the Site;
h) Materials received at job Site;; and
i) A list of all visitors at the Site; and.
j) Any other relevant information deemed relevant as to activities on the Site that day.
2.5.9.2 The CM@Risk shall provide copies of the daily logs to the Owner on a weekly basis. The daily log shall not constitute written notice to the Owner of any event or occurrence when such notice is required by the Contract Documents.
2.5.9.3 Any changes affecting previously approved Work shall require prior written approval of the Owner.