DAILY REPORTS BY CONTRACTOR. At the close of each working day, the CONTRACTOR shall submit a daily report to the DISTRICT, ARCHITECT and the Inspector, on forms approved by the DISTRICT, together with applicable delivery tickets, listing all labor, materials, and equipment involved for that day, and for other services and expenditures when authorized concerning Extra Work items. An attempt shall be made to reconcile the report daily, and it shall be signed by the DISTRICT and the CONTRACTOR. In the event of disagreement, pertinent notes shall be entered by each party to explain points which cannot be resolved immediately. Each party shall retain a signed copy of the report. Reports by Subcontractors or others shall be submitted through the CONTRACTOR. a. Labor. The report shall show names of workers, classifications, and hours worked and hourly rate. Project Superintendent expenses are not allowed.