Damage to Work. If Construction Manager causes damage to the property of Separate Contractors or to other work or property on the Project Site, Construction Manager shall promptly remedy such damage as provided in this Agreement. If any Separate Contractor causes damage to the Work, and Construction Manager is required to remedy such damage, Owner will issue a Change Order for the cost thereof, and will further grant a Time Extension or, alternatively, Owner may direct and compensate Construction Manager for Acceleration, if the delayed activity is on the Critical Path of the Project Schedule.
Appears in 2 contracts
Sources: Construction Management Agreement (New York Times Co), Construction Management Agreement (New York Times Co)