Damages for delay by the SPD. In the event that (i) the SPD does not procure fulfilment of any or all of the Conditions Precedent set forth in Clause 4.1.3 within a period of 90 (Ninety) days from the date of this Agreement, and
Appears in 1 contract
Sources: Power Purchase Agreement (Ppa)
Damages for delay by the SPD. In the event that (i) the SPD does not procure fulfilment of any or all of the Conditions Precedent set forth in Clause 4.1.3 within a period specified in Schedule N and (ii) the delay has not occurred as a result of 90 (Ninety) days from failure to fulfil the date of this Agreement, andobligations under Clause
Appears in 1 contract
Sources: Power Purchase Agreement