Common use of Day works Clause in Contracts

Day works. a. Total may direct the Sub-Contractor to carry out a Variation (or part thereof) as day works. b. The Sub-Contractor must record for each day it has worked on the Variation all resources and present that record to Total for signing the next day (as a precondition to payment). c. Unless the subject of a direction pursuant to clause 11.1 that the Day Works are a Variation to the Sub-Contract, the signing of Day Work dockets are for record purposes only and entitlement to a variation will be assessed in accordance with the Sub-Contract.

Appears in 2 contracts

Sources: Sub Contract Agreement, Sub Contract Agreement