DBE Monthly Utilization Progress Reports. Developer shall submit to ADOT as part of each monthly Draw Request a DBE Monthly Utilization Progress Report for DBE activities completed during the preceding month. Each report shall include:  Progress on various components of the DBE Utilization Plan  Current month and year-to-date summary of DBE Subcontract awards compared to total Subcontract awards  Progress toward the DBE Goals  Summary of work items not yet completed or subcontracted which are targeted for DBE utilization in the coming month and quarter  Bidder’s List Forms of firms who quoted or bid on Subcontracts during the previous month (using Bidder’s List Form).  A separate DBE Intended Affidavit Summary for each of (a) Professional Services, (b) Construction for all DBEs authorized under Sections 12.02 and