DEADLINE FOR THE EXECUTION OF CONTRACTS. (1) The contracts must be executed within a maximum of 2 years from the end date of contracting. (2) The deadline for the execution of contracts may be extended before its end date in duly justified cases.
Appears in 5 contracts
Sources: Financing Agreement, Financing Agreement, Financing Agreement
DEADLINE FOR THE EXECUTION OF CONTRACTS. (1) The contracts must be executed within a maximum of 2 two years from the end date of contracting.
(2) The deadline for the execution of contracts may be extended before its end date in duly justified cases. može prije isteka biti produljen na najviše tri godine od datu- ma sklapanja ovog Sporazuma.
(3) Sva sredstva za koja ugovor nije sklopljen prije isteka roka ugo- varanja, otkazuju se.
Appears in 1 contract
Sources: Financing Agreement
DEADLINE FOR THE EXECUTION OF CONTRACTS. (1) The contracts must be executed within a maximum of 2 two years from the end date of contracting, with the exception of projects nr. 2, 3, 4, 10, 11 and 12, where the works concerning infrastructures justify four years.
(2) The deadline for the execution of contracts may be extended before its end date in duly justified cases.
Appears in 1 contract