Delay and Disruption Damages. Design-Build Contractor shall not be entitled to compensation for delay and disruption damages or for any other increased costs attributable to delays described in this Section 6.8, except as otherwise expressly provided in Sections 6.4.2, 6.8.2.3 or 13.5.2.
Appears in 3 contracts
Sources: Public Private Agreement, Public Private Agreement, Public Private Agreement