Common use of Delay Costs Clause in Contracts

Delay Costs. If the Supplier is responsible for the delay, the Supplier will reimburse Amplitel for any additional substantiated costs reasonably incurred by Amplitel during any extension granted under cl 3.2, which will be reduced to the extent that Amplitel is responsible for the delay.

Appears in 2 contracts

Sources: Purchase Agreement, Supply Agreement