Delay in Commercial Operations Sample Clauses

The 'Delay in Commercial Operations' clause defines the procedures and consequences when a project or facility does not begin its intended commercial activities by the agreed-upon date. Typically, this clause outlines the responsibilities of the parties in the event of a delay, such as notification requirements, potential penalties, or extensions of time. For example, if a power plant fails to start supplying electricity on schedule, the clause may require the operator to pay liquidated damages or provide a revised timeline. Its core function is to allocate risk and incentivize timely completion, ensuring that both parties are protected against losses resulting from operational delays.
POPULAR SAMPLE Copied 2 times
Delay in Commercial Operations. If the Commercial Operations Date has not occurred by the Required Commercial Operations Date (as such date may have been extended as a consequence of a Force Majeure Event), the Company shall pay BPDB, Monthly in arrears until the Commercial Operations Date, as liquidated damages for delays in Commissioning of the Facility, an amount equal to the product of (a) $100.00 and (b) the Contracted Facility Capacity in MW for each Day (or any fraction thereof) of delay of the Commercial Operations Date beyond the Required Commercial Operations Date. In no event shall the total amount of damages assessed under this Section 8.1 exceed twelve (12) Months of liquidated delay damages.
Delay in Commercial Operations. (i) If the Simple Cycle Commercial Operations Date has not occurred by the Required Simple Cycle Commercial Operations Date (as such date may have been extended as a consequence of a Force Majeure Event), the Company shall pay BPDB, Monthly in arrears until the Simple Cycle Commercial Operations Date, as liquidated damages for delays in Commissioning as a Simple Cycle Unit, an amount equal to the product of (a) $50.00 and (b) the Contracted Simple Cycle Capacity in MW for each Day (or any fraction thereof) of delay of the Simple Cycle Commercial Operations Date beyond the Required Simple Cycle Commercial Operations Date. In no event shall the total amount of damages assessed under this Section 8.1 exceed twelve (12) Months of liquidated delay damages. (ii) If the Commercial Operations Date has not occurred by the Required Commercial Operations Date (as such date may have been extended as a consequence of a Force Majeure Event), the Company shall pay BPDB, Monthly in arrears until the Commercial Operations Date, as liquidated damages for delays in Commissioning of the Facility as a Combined Cycle Unit, an amount equal to the product of (a) $100.00 and (b) the Contracted Facility Capacity in MW for each Day (or any fraction thereof) of delay of the Commercial Operations Date beyond the Required Commercial Operations Date. In no event shall the total amount of damages assessed under this Section 8.1 exceed twelve (12) Months of liquidated delay damages.
Delay in Commercial Operations. In the event (a) the Ammonia Plant is not 100% converted to using coal as a feedstock instead of natural gas and (b) the Ammonia Plant has not commenced commercial operations, in each case of (a) and (b) by March 31, 2008 (subject to extension for each day of delay due to force majeure (defined as acts of God, acts of war, acts of terrorism, accidental property damage and labor strikes) provided the Company is diligently working to meet the conditions specified in (a) and (b)), the Exercise Price existing immediately prior to such default shall, on April 1, 2008 be reduced to 50% of the Exercise Price in effect immediately prior thereto.
Delay in Commercial Operations. If the Commercial Operations Date has not occurred by the Required Commercial Operations Date (as such date may have been extended as a consequence of a Force Majeure Event or Political Event or Change in Law in accordance with the terms of this Agreement and Implementation Agreement), the Company shall pay BPDB, Monthly in arrears until the Commercial Operations Date, as liquidated damages for delays in Commissioning of the Facility, an amount equal to the product of (a) $50.00 and (b) the Contracted Capacity in MW for each Day (or any fraction thereof) of delay of the Commercial Operations Date beyond the Required Commercial Operations Date. In no event shall the total amount of damages assessed under this Section 8.1 exceed twelve (12) Months of liquidated delay damages.
Delay in Commercial Operations. Hydrogen shall be available for supply to Sunoco from the BOC Facility at substantially the quantities and specifications set forth in this Agreement on February 1, 2006, as such date may be extended by any Force Majeure Event and delays caused by Sunoco’s failure to (a) prepare and deliver the site of the BOC Facility Premises by the site preparation dates set forth on Schedule 2.3 and in the manner set forth in the Construction Agreement and Lease Agreement and/or (b) Sunoco’s failure to deliver the Feedstock and Utilities at the times and in the quantities and meeting the specifications set forth in this Agreement and/or (c) accept Steam and/or Hydrogen at the times and in the amount set forth in this Agreement (such date, as extended hereunder, the “Commercial Operations Date”); provided that, in no event can the Commercial Operations Date start on any day during Phase V.

Related to Delay in Commercial Operations

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Synchronization, Commissioning and Commercial Operation 5.1.1 The SPG shall give PGVCL at least thirty (30) days’ advanced preliminary written notice and at least fifteen (15) days’ advanced final written notice, of the date on which it intends to synchronize the Solar Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/ and checking/verification is made by the concerned authorities of the PGVCL. 5.1.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject in-firm power to grid from time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project. 5.1.5 The SPG shall commission the Project within nine (9) Months from the Date of execution of this PPA. Declaration of COD shall be certified by the commissioning committee. 5.1.6 The Parties agree that for the purpose of commencement of the supply of electricity by SPG to PGVCL, liquidated damages for delay etc., the Scheduled Commissioning Date as defined in this Agreement shall be the relevant date.

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • Commercial Diligence Pfizer will use Commercially Reasonable Efforts to Commercialize a given Agreement Product in each Major Market Country in the Field in the Territory where Pfizer or its Affiliates have received Regulatory Approval for such Agreement Product. Pfizer will have no other diligence obligations with respect to the Commercialization of Agreement Products under this Agreement.

  • Development Diligence Pfizer will use its Commercially Reasonable Efforts to Develop and seek Regulatory Approval for one Product in the Field in [***]. Pfizer will have no other diligence obligations with respect to the Development or Regulatory Approval of Products under this Agreement.