Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWC, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:
Appears in 21 contracts
Sources: Framework Contract for Travel Services, Framework Contract for Supplies, Framework Contract for Supplies
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWCcontract, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:
Appears in 4 contracts
Sources: Contract for Supplies, Contract for Supplies, Contract for Supplies
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWCcontract, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:
Appears in 3 contracts
Sources: Draft Contract for Supplies, Contract for Supplies, Contract for Supplies
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWC, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:
Appears in 2 contracts
Sources: Framework Contract for Supplies, Framework Contract for Supplies
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWCcontract, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:), where V is the price of the deliverable or result or, failing that, the amount specified in the purchase order;
Appears in 2 contracts
Sources: Service Contract, Service Contract
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWCFWC or a specific contract, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:
Appears in 1 contract
Sources: Framework Contract for Supplies
Delay in Delivery. If the contractor fails to perform its contractual obligations within the applicable time limits set out in this FWCFWC or the relevant order form or specific contract, the contracting authority may claim liquidated damages for each day of delay using the following formula: 0.3 x (V/d) where:: Liquidated damages may be imposed together with a reduction in price under the conditions laid down in Article II.15.
Appears in 1 contract
Sources: Framework Contract