Common use of Delay Payments Clause in Contracts

Delay Payments. 29.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 14 (Charges) shall apply in relation to the payment of Delay Payments. 29.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where: (a) the Authority is entitled to or does terminate this Agreement pursuant to Clause 34.1(b) (Termination by the Authority); or (b) the Delay exceeds the Delay Deduction Period.

Appears in 1 contract

Sources: Model Services Agreement

Delay Payments. 29.1 28.1 If a Key Authority to Proceed Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 14 7.1 (ChargesCharges and Invoicing) shall apply in relation to the payment of Delay Payments. 29.2 28.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Authority to Proceed Milestone by its Milestone Date except where: (a) the Authority is entitled to or does terminate this Agreement pursuant to Clause 34.1(b33.1(b) (Termination by the Authority); or (b) the Delay exceeds the Delay Deduction Period.

Appears in 1 contract

Sources: Service Agreement

Delay Payments. 29.1 28.1 If a Key Milestone has not been Achieved by its relevant Milestone Date, the provisions of Paragraph 1 of Part C of Schedule 14 7.1 (ChargesCharges and Invoicing) shall apply in relation to the payment of Delay Payments. 29.2 28.2 Delay Payments shall be the Authority's exclusive financial remedy for the Supplier’s failure to Achieve a Key Milestone by its Milestone Date except where: (a) the Authority is entitled to or does terminate this Agreement pursuant to Clause 34.1(b33.1(b) (Termination by the Authority); or (b) the Delay exceeds the Delay Deduction Period.

Appears in 1 contract

Sources: Ict Contract