Common use of Delays in the Project Schedule Clause in Contracts

Delays in the Project Schedule. In the event that the CMTISP’s field or technical work is delayed or interrupted due to causes beyond their control, the CMTISP may submit a request for a Change Order for the labor, equipment and other costs the CMTISP incurs in order to maintain their workforce for the Owner’s benefit during an interruption or delay resulting from a non-scheduled standby time, and any attendant costs of demobilization and subsequent remobilization; such request for a Change Order shall be based upon (1) documentation to establishing the scheduling of testing or inspection services and the reason for the delay in the ability of the CMTISP to perform the testing and/or inspection services, and

Appears in 2 contracts

Sources: Construction Materials Testing & Inspection Services Agreement, Construction Materials Testing & Inspection Services Agreement