Deliverable review Sample Clauses

Deliverable review. Upon submission, DMC requires up to 10 working days in Phase 1 and up to 20 working days in the other phases to review. The approval may require multiple rounds of review cycles subject to the discretion of the Museum. Plan for at least 2 cycles at each phase. If, in the opinion of the Museum, any deliverable does not satisfy the requirements set forth in this Agreement, and after all options have been explored with the Organization, the Museum can, as appropriate and in its sole discretion, cancel any payment or part thereof.
Deliverable review. Without obligation to do so, SHAMROCK CIVIL may provide the Consultant with such comment, information or advice as it considers appropriate to provide. Any comment, information or advice provided: (a) is intended to be of assistance to the Consultant and shall not be construed as a direction from SHAMROCK CIVIL to the Consultant; (b) shall not be taken as Approval of Services that do not conform to the Agreement; and (c) shall not waive any provisions of or release the Consultant from its obligations under the Agreement.
Deliverable review a. All deliverables for this task will be reviewed by the City and the City will provide comments back to Contractor within 2 weeks.

Related to Deliverable review

  • Project Review A. Programmatic Allowances 1. If FEMA determines that the entire scope of an Undertaking conforms to one or more allowances in Appendix B of this Agreement, with determinations for Tier II Allowances being made by SOI-qualified staff, FEMA shall complete the Section 106 review process by documenting this determination in the project file, without SHPO review or notification. 2. If the Undertaking involves a National Historic Landmark (NHL), FEMA shall notify the SHPO, participating Tribe(s), and the NPS NHL Program Manager of the NPS Midwest Regional Office that the Undertaking conforms to one or more allowances. FEMA shall provide information about the proposed scope of work for the Undertaking and the allowance(s) enabling FEMA’s determination. 3. If FEMA determines any portion of an Undertaking’s scope of work does not conform to one or more allowances listed in Appendix B, FEMA shall conduct expedited or standard Section 106 review, as appropriate, for the entire Undertaking in accordance with Stipulation II.B, Expedited Review for Emergency Undertakings, or Stipulation II.C, Standard Project Review. 4. Allowances may be revised and new allowances may be added to this Agreement in accordance with Stipulation IV.A.3, Amendments. B. Expedited Review for Emergency Undertakings

  • Independent Review Contractor shall provide the Secretary of ADS/CIO an independent expert review of any Agency recommendation for any information technology activity when its total cost is $1,000,000.00 or greater or when CIO requires one. The State has identified two sub-categories for Independent Reviews, Standard and Complex. The State will identify in the SOW RFP the sub-category they are seeking. State shall not consider bids greater than the maximum value indicated below for this category. Standard Independent Review $25,000 Maximum Complex Independent Review $50,000 Maximum Per Vermont statute 3 V.S.A. 2222, The Secretary of Administration shall obtain independent expert review of any recommendation for any information technology initiated after July 1, 1996, as information technology activity is defined by subdivision (a) (10), when its total cost is $1,000,000 or greater or when required by the State Chief Information Officer. Documentation of this independent review shall be included when plans are submitted for review pursuant to subdivisions (a)(9) and (10) of this section. The independent review shall include: • An acquisition cost assessment • A technology architecture review • An implementation plan assessment • A cost analysis and model for benefit analysis • A procurement negotiation advisory services contract • An impact analysis on net operating costs for the agency carrying out the activity In addition, from time to time special reviews of the advisability and feasibility of certain types of IT strategies may be required. Following are Requirements and Capabilities for this Service: • Identify acquisition and lifecycle costs; • Assess wide area network (WAN) and/or local area network (LAN) impact; • Assess risks and/or review technical risk assessments of an IT project including security, data classification(s), subsystem designs, architectures, and computer systems in terms of their impact on costs, benefits, schedule and technical performance; • Assess, evaluate and critically review implementation plans, e.g.: • Adequacy of support for conversion and implementation activities • Adequacy of department and partner staff to provide Project Management • Adequacy of planned testing procedures • Acceptance/readiness of staff • Schedule soundness • Adequacy of training pre and post project • Assess proposed technical architecture to validate conformance to the State’s “strategic direction.” • Insure system use toolsets and strategies are consistent with State Chief Information Officer (CIO) policies, including security and digital records management; • Assess the architecture of the proposed hardware and software with regard to security and systems integration with other applications within the Department, and within the Agency, and existing or planned Enterprise Applications; • Perform cost and schedule risk assessments to support various alternatives to meet mission need, recommend alternative courses of action when one or more interdependent segment(s) or phase(s) experience a delay, and recommend opportunities for new technology insertions; • Assess the architecture of the proposed hardware and software with regard to the state of the art in this technology. • Assess a project’s backup/recovery strategy and the project’s disaster recovery plans for adequacy and conformance to State policy. • Evaluate the ability of a proposed solution to meet the needs for which the solution has been proposed, define the ability of the operational and user staff to integrate this solution into their work.

  • Log Reviews All systems processing and/or storing PHI COUNTY discloses to 11 CONTRACTOR or CONTRACTOR creates, receives, maintains, or transmits on behalf of COUNTY 12 must have a routine procedure in place to review system logs for unauthorized access.

  • Deliverables Upon satisfactory completion of the work authorization, the Engineer shall submit the deliverables as specified in the executed work authorization to the State for review and acceptance.

  • Acceptance Tests 11.1 If the Contract provides acceptance tests for Goods and/or the result of Services after their completion and/or delivery to the Purchaser, the acceptance shall only be considered as definitive when such tests have demonstrated the compliance of the Goods and/or the result of the Services to the requirements in the Contract. 11.2 Where the Contract provides for an acceptance procedure in the presence of both parties, at the successful completion of such procedure, the Purchaser shall issue the Supplier with an acceptance certificate which shall authorise the Supplier to invoice the Purchaser for any payment due on such acceptance. 11.3 The Purchaser shall at its discretion be entitled to issue and acceptancecertificate with reserves. The Supplier shall be obliged to remedy any non-conformities within the period set out in the acceptance certificate. Any payment which would otherwise have been due on acceptance may be withheld by the Purchaser in whole or part until the non- conformities underlying the reserves have been remedied.