Delivery of Request for Change Order. Design-Builder shall deliver a Request for Change Order to VPRA within sixty (60) Days after Design-Builder’s delivery of the Change Notice. If Design-Builder fails to submit a complete Request for Change Order within sixty (60) Days after Design-Builder’s delivery of the Change Notice, Design-Builder shall be deemed to have irrevocably and forever waived and released any right to any relief whatsoever for any effect attributable or related to the Relief Event and the acts or omissions comprising such Relief Event; provided, however, that if Design-Builder submits a Request for Change Order within sixty (60) Days of the date of Design-Builder’s delivery of the Change Notice and VPRA responds as provided in Section 12.5.1 that Design-Builder’s Request for Change Order is incomplete, Design-Builder shall have until the later of (a) fifteen (15) Days after receipt of VPRA’s notice pursuant to Section 12.5.1 or (b) sixty (60) Days after Design- Builder’s delivery of the Change Notice, to comply in full with Section 12.4.1 before the waiver herein becomes effective.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement