Delivery Responsibility. Unless agreed otherwise by the Parties, Contractor shall be responsible for the safe delivery of all Materials and Equipment to the Site. Contractor shall abide by the requirements of the Contract and the Specifications for delivery of major items of Equipment, or Materials to the Site and shall provide Company no less than thirty (30) days notice of the date on which any major item of Equipment or Materials will be delivered to the Site. Contractor shall be responsible for the reception, unloading, storage and protection on Site of all Equipment or Materials delivered for the purposes of this Contract, including (unless agreed otherwise by the Parties with respect to such item of Company-Procured Equipment) all Company-Procured Equipment.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Contract (Chugach Electric Association Inc), Engineering, Procurement and Construction Contract (Chugach Electric Association Inc)