Detailed Claim Sample Clauses

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. The Consultant shall not be entitled to claim any such additional compensation, or extension of time, unless within 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the City, the Consultant has given the City a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. Within five (5) Business Days after giving a written notice in accordance with sub-clause 14.1 [Notice of intent to claim], the Sub- Contractor must submit a written claim which must include: a. detailed particulars concerning the matter or thing, or direction, on which the claim is based; b. the legal basis of the claim; c. the facts relied on to support the claim; and d. details of the amount claimed and how it has been calculated.
Detailed Claim. The Consultant shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the date of the Notice of Claim, and before final payment by the County, the Consultant has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or extension of time claimed to be due.
Detailed Claim. The SUBRECIPIENT shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the COUNTY, the SUBRECIPIENT has given the COUNTY a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. The Contractor shall not be entitled to claim any such additional compensa- tion, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contrac- tor has given the County a detailed written statement of each element of cost or other com- pensation requested and of all elements of additional time required, and copies of any sup- porting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. LLLT shall not be entitled to claim any such additional compensation, or extension of time, unless within 30 days of the accomplishment of the portion of the work from which the claim arose, and before formal payment by County, LLLT has given County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. The Engineer shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the District, the Engineer has given the District a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.
Detailed Claim. The CONTRACTOR shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the COUNTY, the CONTRACTOR has given the COUNTY a detailed written statement of each element of cost or ARC Tactical other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Related to Detailed Claim

  • Disputed Claims 4.1 Notwithstanding paragraph 4.5 of this Schedule, payment by the Authority of all or any part of any invoice rendered or other claim for payment by the Contractor shall not signify approval of such invoice/claim. The Authority reserves the right to verify invoices/claims after the date of payment and subsequently to recover any sums which have been overpaid. 4.2 If any part of a claim rendered by the Contractor is disputed or subject to question by the Authority either before or after payment then the Authority may call for the Contractor to provide such further documentary and oral evidence as it may reasonably require to verify its liability to pay the amount which is disputed or subject to question and the Contractor shall promptly provide such evidence in a form satisfactory to the Authority. 4.3 If any part of a claim rendered by the Contractor is disputed or subject to question by the Authority, the Authority shall not withhold payment of the remainder. 4.4 If any invoice rendered by the Contractor is paid but any part of it is disputed or subject to question by the Authority and such part is subsequently agreed or determined not to have been properly payable then the Contractor shall forthwith repay such part to the Authority. 4.5 The Authority shall be entitled to deduct from sums due to the Contractor by way of set-off any amounts owed to it or which are in dispute or subject to question either in respect of the invoice for which payment is being made or any previous invoice.

  • Direct Claims Any Action by an Indemnified Party on account of a Loss which does not result from a Third Party Claim (a “Direct Claim”) shall be asserted by the Indemnified Party giving the Indemnifying Party reasonably prompt written notice thereof, but in any event not later than 30 days after the Indemnified Party becomes aware of such Direct Claim. The failure to give such prompt written notice shall not, however, relieve the Indemnifying Party of its indemnification obligations, except and only to the extent that the Indemnifying Party forfeits rights or defenses by reason of such failure. Such notice by the Indemnified Party shall describe the Direct Claim in reasonable detail, shall include copies of all material written evidence thereof and shall indicate the estimated amount, if reasonably practicable, of the Loss that has been or may be sustained by the Indemnified Party. The Indemnifying Party shall have 30 days after its receipt of such notice to respond in writing to such Direct Claim. The Indemnified Party shall allow the Indemnifying Party and its professional advisors to investigate the matter or circumstance alleged to give rise to the Direct Claim, and whether and to what extent any amount is payable in respect of the Direct Claim and the Indemnified Party shall assist the Indemnifying Party’s investigation by giving such information and assistance (including access to the Company’s premises and personnel and the right to examine and copy any accounts, documents or records) as the Indemnifying Party or any of its professional advisors may reasonably request. If the Indemnifying Party does not so respond within such 30 day period, the Indemnifying Party shall be deemed to have rejected such claim, in which case the Indemnified Party shall be free to pursue such remedies as may be available to the Indemnified Party on the terms and subject to the provisions of this Agreement.