Common use of DETAILED WORK SCHEDULE Clause in Contracts

DETAILED WORK SCHEDULE. D13.1 The Contractor shall provide the Contract Administrator with a detailed work schedule at least two (2) Business Days prior to the commencement of any Work on the Site but in no event later than the date specified in C4.1 for the return of the executed Contract. D13.2 The detailed work schedule shall consist of the following: (a) a critical path method (C.P.M.) schedule for the Work; and (b) a ▇▇▇▇▇ chart for the Work based on the C.P.M. schedule; all acceptable to the Contract Administrator. D13.3 Further to D13.2(a), the C.P.M. schedule shall clearly identify the start and completion dates of all of the following activities/tasks making up the Work as well as showing those activities/tasks on the critical path: (a) Commencement Date. (b) Installation of Land Drainage Sewers on a street by street basis. (c) Surface restoration. (d) Substantial Performance. (e) Total Performance.

Appears in 3 contracts

Sources: Bid Opportunity, Bid Opportunity, Bid Opportunity