Developer completion notice Sample Clauses
A Developer Completion Notice clause requires the developer to formally notify relevant parties when a construction or development project has reached substantial or final completion. Typically, this notice is provided in writing and may trigger subsequent actions such as inspections, handover procedures, or the commencement of warranty periods. The core function of this clause is to establish a clear and official point at which the developer's obligations regarding completion are recognized, thereby reducing ambiguity and facilitating the transition to the next phase of the project.
POPULAR SAMPLE Copied 1 times
Developer completion notice. When, in the reasonable opinion of the Developer, the Developer’s Works have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Developer’s Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material reasonably required for the City to assume responsibility for the Developer’s Works; and
(c) at least three sets of the “as built” drawings of the Developer’s Works, including one set in electronic format, (Completion Notice). For the avoidance of doubt, the Developer can issue separate Completion Notices at separate times for different elements of the Developer’s Works, however the Developer must ensure that Completion is achieved for the Developer’s Works before the due date specified in Item 1 of Schedule 3.
Developer completion notice. When, in the reasonable opinion of the Developer, the Developer’s Works have reached Completion, and all hold points inspections have been approved by the City (whose approval must not be unreasonably withheld), the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Developer’s Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material reasonably required for the City to assume responsibility for the Developer’s Works; and
(c) at least two sets of the “as built” drawings of the Developer’s Works, including one set in electronic format, prepared in accordance with the City’s Public Domain Manual and Technical Specifications, (Completion Notice). For the avoidance of doubt, the Developer can issue separate Completion Notices at separate times for different elements of the Developer’s Works, however the Developer must ensure that Completion is achieved for the Developer’s Works before the due date specified in Item 1 of Schedule 3.
Developer completion notice. When, in the reasonable opinion of the Developer and the Landowner, the Developer’s Works have reached Completion, the Developer and the Landowner must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Developer’s Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material reasonably required by the City; and
(c) at least two sets of the “as built” drawings of the Developer’s Works, including one set in electronic format, , prepared in accordance with the City’s Public Domain Manual and Technical Specifications or other policies as applicable, (Completion Notice). For the avoidance of doubt, the Developer and the Landowner can issue separate Completion Notices at separate times for different elements of the Developer’s Works, however the Developer and the Landowner must ensure that Completion is achieved for the Developer’s Works before the due date specified in clause 1 of Schedule 3.
Developer completion notice. Public Benefits When, in the reasonable opinion of the Developer, a Public Benefit has reached Completion, the Developer must notify the City’s Representative in writing and must include in or attached to that notice:
(a) In relation to the Public Art prior to the issue of the Occupation Certificate for the Development:
(i) a statement that the Public Art installation has been completed;
(ii) a copy of the draft Final Public Art Report (Final Report) in electronic format for the approval of the City;
(iii) copies of any warranties, guarantees, maintenance information or other material in the possession of the Developer reasonably required for the City to assume responsibility for the Public Art on City Land.
(iv) copies of any warranties, contractual arrangements, guarantees, insurance policies or other evidence that Public Art not installed on City Land will be adequately maintained during the Defects Liability Period (if applicable).
(b) If the City has elected not to take ownership of the Public Art, the Developer must enter into an agreement with the City for the installation of the Public Art on the City Land in accordance with clause 5.1 (b) of Schedule 3. (Completion Notice). For the avoidance of doubt, the Developer can issue separate Completion Notices at separate times for different elements of the Public Benefits, however the Developer must ensure that Completion is achieved for the Public Benefits before the due date specified in Item 1 of Schedule 3.
Developer completion notice. (a) When, in the reasonable opinion of the Developer, construction of the Logistics Hub is about to reach Completion, the Developer must notify the City’s Representative in writing, with such notice to include a statement from the superintendent under the Building Contract that in their opinion the Logistics Hub is about to reach Completion (Completion Notice).
(b) The City must procure that the City’s Representative inspects the Logistics Hub within 5 Business Days of the date that the Completion Notice is received by the City. Within 5 Business Days of the date of the inspection by the City’s Representative, the City may (acting reasonably) notify the Developer in writing if any of the requirements in the following clauses of Annexure A have not been met:
(i) clause 1(a);
(ii) clause 1(c); and
(iii) clause 1(h).
(c) If a notice is issued by the City pursuant to clause 6.2(b), the Developer must promptly take all action required to meet the relevant requirements.
(d) If the Developer disputes a notice served by the City pursuant to clause 6.2(b), such dispute will be resolved pursuant to clause 11.
Developer completion notice. When, in the reasonable opinion of the Developer, the Developer’s Works have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Developer’s Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material in the possession of the Developer reasonably required for the City to assume responsibility for the Developer’s Works on land it owns or will own;
(c) at least three sets of the “as built” drawings of the Developer’s Works situated on City Land, including one set in electronic format; and
(d) copies of any warranties, contractual arrangements, guarantees, insurance policies or other evidence that Developer’s Works not on City Land will be adequately maintained during the Defects Liability Period.
Developer completion notice. When, in the reasonable opinion of the Developer, the Developer’s Works have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Developer’s Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material reasonably required for the City to assume responsibility for the Developer’s Works; and
Developer completion notice. When, in the reasonable opinion of the Developer, the Environmental Excellence Initiatives have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a copy of:
(i) the executive summary of the Energy Efficient Review prepared by a ▇▇▇▇▇▇ certified Independent Design Reviewer in accordance with the ▇▇▇▇▇▇ requirements; and
(ii) 12 months of sub-metering data for energy and water that informed the ▇▇▇▇▇▇ rating
(b) evidence that the ▇▇▇▇▇▇ rating for Energy and Water has been achieved, (Completion Notice). For the avoidance of doubt, the Developer can issue separate Completion Notices at separate times for different elements of the Environmental Excellence Initiatives, however the Developer must ensure that Completion is achieved for the Environmental Excellence Initiatives before the due date specified in Item 1 of Schedule 3.
Developer completion notice. When, in the reasonable opinion of the Developer, the Footpath Works have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion that the Footpath Works have reached Completion;
(b) copies of any warranties, guarantees, maintenance information or other material reasonably required for the City to assume responsibility for the Foothpath Works; and
(c) at least three sets of the “as built” drawings of the Foothpath Works, including one set in electronic format,
Developer completion notice. When, in the reasonable opinion of the Developer, the Affordable Housing Units and the Car Park Lots have reached Completion, the Developer must notify the City’s Representative in writing and must include in that notice:
(a) a statement from the person with direct responsibility and supervision of that work that in their opinion the Affordable Housing Units and Car Park Lots have reached Completion;
(b) a statement from the Community Housing Provider that has entered into a Contract of Sale with the Developer for the Affordable Housing Units and Car Park Lots that it is satisfied that the Affordable Housing Units and Car Park Lots have reached Completion.