Development of Architectural Program. Architect shall prepare for District’s review an architectural program as follows: 2.2.1. Perform pre-design investigations to establish appropriate guidelines around which and within which the Project is to be designed. Identify design issues relating to functional needs, directives and constraints imposed by regulatory codes. Review all data pertinent to the Project including survey, site maps, geotechnical reports and recommendations, soil testing results reports, and pertinent historical data, and other relevant information provided by District. 2.2.2. Review applicable code sections of the California Code of Regulations, Title 24, including amendments. 2.2.3. Identify design issues relating to functional needs, directives and constraints imposed by applicable regulatory codes. 2.2.4. Based on survey and topography data provided by District, input into computer and develop existing conditions base for the Schematic Design Phase. 2.2.5. Administer Project as required to coordinate work with District and between Consultants. 2.2.6. Confer with District’s Technology Department to verify technological requirements for the Project.
Appears in 2 contracts
Sources: Architectural Services Agreement, Architectural Services Agreement
Development of Architectural Program. Architect shall prepare for District’s review an architectural program a preliminary design approach as follows:
2.2.1. Perform pre-design pre‐design investigations to establish appropriate guidelines around which and within which the Project is to be designed. Identify design issues relating to functional needs, directives and constraints imposed by regulatory codes. Review all data pertinent to the Project including survey, site maps, geotechnical reports and recommendations, soil testing results reports, and pertinent historical data, and other relevant information provided by District.
2.2.2. Review applicable code sections of the California Code of Regulations, Title 24, including amendments.
2.2.3. Identify design issues relating to functional needs, directives and constraints imposed by applicable regulatory codes.
2.2.4. Based on survey and topography data provided by District, input into computer and develop existing conditions base for the Schematic Design Construction Document Phase.
2.2.5. Administer Project as required to coordinate work with District and between Consultants.
2.2.6. Confer with District’s Technology Department to verify technological requirements for the Project.