DISAPPROVED SUBMITTALS. Contractor shall make corrections required by the government and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the KO, COR, and Government PM. If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. Until the changed submittals are approved, the Contractor cannot proceed with other related order/contract effort which is dependent on the acceptance of the approved submittals.